Comparison Of Installation Wages for Granite Tiles in Large and Small Spaces Using the Method Productivity Delay Model
10 Halaman
Penulis
ISSN
2621-5276
Penerbit
Universitas Pendidikan Nasional
Diterbitkan pada
17/04/2025
Bahasa
English
Kata Kunci
Abstrak
Labor performance is a key factor in the completion of construction projects. The installation of granite tiles in confined areas presents unique challenges due to the high number of unusable tile cuts, which can increase costs beyond the project’s budget plan (RAB). This study analyzes labor performance in granite tile installation across narrow and spacious areas, focusing on its impact on construction cost efficiency. Work in confined areas is more complex due to excessive cutting waste, often resulting in actual costs exceeding the planned budget. The study aims to determine the labor coefficient and compare the unit labor costs between the two working conditions. Field observations were carried out using the MPDM to measure worker productivity, including delay time in each work cycle. This quantitative research was conducted on a hotel project that used 40 × 40 cm granite tiles. The results showed that the labor coefficient for tile installation in spacious areas was 0.124, while in confined areas it was 0.136. The labor cost per square meter was recorded at Rp 44,400 in spacious areas and Rp 45,864 in confined areas. This study provides practical contributions to labor cost planning and technical insights for preparing unit price analysis to improve efficiency in construction projects.